| 
					
				 | 
			
			
				@@ -5430,9 +5430,9 @@ optional.  The individual parts have the following meaning: 
			 | 
		
	
		
			
				 | 
				 | 
			
			
				 The =est+= summary type requires further explanation.  It is used for 
			 | 
		
	
		
			
				 | 
				 | 
			
			
				 combining estimates, expressed as low-high ranges.  For example, 
			 | 
		
	
		
			
				 | 
				 | 
			
			
				 instead of estimating a particular task will take 5 days, you might 
			 | 
		
	
		
			
				 | 
				 | 
			
			
				-estimate it as 5-6 days if you're fairly confident you know how much 
			 | 
		
	
		
			
				 | 
				 | 
			
			
				-work is required, or 1-10 days if you do not really know what needs to 
			 | 
		
	
		
			
				 | 
				 | 
			
			
				-be done.  Both ranges average at 5.5 days, but the first represents 
			 | 
		
	
		
			
				 | 
				 | 
			
			
				+estimate it as 5--6 days if you're fairly confident you know how much 
			 | 
		
	
		
			
				 | 
				 | 
			
			
				+work is required, or 1--10 days if you do not really know what needs 
			 | 
		
	
		
			
				 | 
				 | 
			
			
				+to be done.  Both ranges average at 5.5 days, but the first represents 
			 | 
		
	
		
			
				 | 
				 | 
			
			
				 a more predictable delivery. 
			 | 
		
	
		
			
				 | 
				 | 
			
			
				  
			 | 
		
	
		
			
				 | 
				 | 
			
			
				 When combining a set of such estimates, simply adding the lows and 
			 | 
		
	
	
		
			
				| 
					
				 | 
			
			
				@@ -5442,7 +5442,7 @@ estimate from the sum.  For example, suppose you had ten tasks, each 
			 | 
		
	
		
			
				 | 
				 | 
			
			
				 of which was estimated at 0.5 to 2 days of work.  Straight addition 
			 | 
		
	
		
			
				 | 
				 | 
			
			
				 produces an estimate of 5 to 20 days, representing what to expect if 
			 | 
		
	
		
			
				 | 
				 | 
			
			
				 everything goes either extremely well or extremely poorly.  In 
			 | 
		
	
		
			
				 | 
				 | 
			
			
				-contrast, =est+= estimates the full job more realistically, at 10-15 
			 | 
		
	
		
			
				 | 
				 | 
			
			
				+contrast, =est+= estimates the full job more realistically, at 10--15 
			 | 
		
	
		
			
				 | 
				 | 
			
			
				 days. 
			 | 
		
	
		
			
				 | 
				 | 
			
			
				  
			 | 
		
	
		
			
				 | 
				 | 
			
			
				 Here is an example for a complete columns definition, along with 
			 |